Nitin Gadkari: 725 Road Projects Face Delays As A Result Of Erratic Rainfall

As many as 725 road projects of the total 1,801 ongoing projects are running behind the schedule across the country as of February 2023 due to protracted monsoon in many states and above-average rainfall in some states, Union minister Nitin Gadkari said on Wednesday.

The Road Transport and Highways Minister in a written reply to the Rajya Sabha said additional cost is not incurred in all delayed projects as in Build-Operate-Transfer (BOT) projects, as escalation cost is absorbed by the Concessionaire. For other projects, if the delay is attributable to the Project Authority, price escalation is paid as per contract conditions, which may or may not result in additional cost, depending upon the final value of price escalation determined on the actual completion of the project and final settlement of bills, he added.

Growth of India

Replying to a separate question, Gadkari said that the National Highways Authority of India has planted 344.27 lakh trees from 2016 to February 2023 under the green highways policy. The ministry of road, transport, and highways promulgated the Green Highways (Plantation, Transplantation, Beautification & Maintenance) Policy – 2015 for the development of green corridors along national highways in the country.

Replying to another question, Gadkari said the Government of India and the World Bank have signed an agreement for the construction of the Green National Highway Corridors Project (GNHCP) in an aggregate length of 781 km in the states of Himachal Pradesh, Rajasthan, Uttar Pradesh, and Andhra Pradesh, with loan assistance of USD 500 million against total project cost of USD 1,288.24 million (Rs 7,662.47 crore).

Also read: Kerala Assembly Witnesses Unprecedented Protest Against Speaker

The objective of the GNHCP is to demonstrate safe and green highways keeping in view climate resilience and the use of green technologies by incorporating the provisions of conservation of natural resources using cement-treated sub-base/reclaimed asphalt pavement, use of local/ marginal material such as lime, fly ash, waste plastic, bio-engineering measures for slope protection such as hydroseeding.

Shruti Chaturvedi

Recent Posts

PM Modi’s Diaspora Outreach Spurs Major FDI From Madhvani Group

Uganda-based industrial conglomerate Madhvani Group has announced investment plans worth up to ₹10,000 crore over…

10 mins ago

Gorakhpur Link Expressway Set To Open Soon; UP CM Yogi To Launch Safety Fleet

UP Chief Minister Yogi Adityanath will inaugurate the much-awaited Gorakhpur Link Expressway on June 20.

20 mins ago

Iran Targets ‘Israeli Intelligence Sites’ In Tel Aviv; Israel Retaliates With Strikes In Western Iran

Iran's Islamic Revolutionary Guard Corps (IRGC) carried out strikes on 'key Israeli intelligence sites' in…

38 mins ago

Air India Cancels Delhi–Paris Flight Amid Ongoing Operational Setbacks

Air India cancelled its Delhi–Paris flight AI 143 on Tuesday after mandatory pre-flight inspections revealed…

48 mins ago

Rains Bring Relief To Delhi-NCR After Intense Heatwave

A sudden spell of rain on Tuesday brought long-awaited relief to residents of Delhi and…

3 hours ago

Google Unveils ‘Safety Charter’ To Strengthen India’s Digital Security

Google launched a major digital safety initiative in India on Tuesday, introducing its new ‘Safety…

4 hours ago