Railway Minister Ashwini Vaishnaw Expresses Satisfaction with Bullet Train Project Progress

Railway Minister Ashwini Vaishnaw, after a thorough assessment of the Mumbai-Ahmedabad bullet train project, commended the satisfactory progress made during a recent review on Thursday. While he refrained from providing a specific completion deadline for the overall project, Vaishnaw emphasized the positive momentum in the work.

“We proceed section by section in a linear project. It is a complex project, and the work is going on at a very good speed,” stated the minister. “After reviewing the project, I am quite satisfied and impressed with its progress.”

The 508-km-long project between Mumbai and Ahmedabad has seen the erection of viaducts covering a length of 272 km. Vaishnaw highlighted the complexity of the route, which includes eight rivers, with bridges already constructed over five of them.

Also Read: Prime Minister Narendra Modi Offers Chadar At Ajmer Sharif Dargah During 812th Urs

Emphasizing specific milestones, the minister reaffirmed that the 50-km-long section between Surat and Billimora is scheduled for completion by 2026, and the work is on track as per the established timeline.

Vaishnaw underscored the economic significance of the bullet train corridor, connecting major economic centers such as Mumbai, Thane, Vapi, Surat, Baroda, Anand, and Ahmedabad. “At many stations, significant progress has been made,” he added.

Providing insights into the project’s unique features, Vaishnaw mentioned the proposal for the bullet train to pass through a sea tunnel to reach Mumbai from Thane, with work on the sea tunnel already underway.

Also Read: Sahibganj DC and CM’s Press Advisor Summoned in Illegal Mining Case; Ambiguity in FIR Noted in Cabinet’s Letter to ED

The Mumbai-Ahmedabad high-speed train corridor, announced in 2017, envisions bullet trains operating at a speed of 320 kmph. Initially slated for completion by 2022, the project’s deadline was extended by the National High-Speed Rail Corporation Limited, the executing body of the project.

Naiteek Bhatt

Recent Posts

Prince William And Princess Catherine To Visit Mumbai For Earthshot Prize Summit And Awards

Prince William and Catherine, the Princess of Wales, will visit Mumbai from November 16 to…

1 hour ago

Lieutenant Governor Dr Dinesh Sharma Highlights Tribal Welfare Initiatives On Janjatiya Gaurav Diwas

Andaman and Nicobar Lieutenant Governor Dr Dinesh Sharma highlighted tribal welfare initiatives, distributed Ayushman Bharat…

2 hours ago

Lieutenant Governor Dr Dinesh Sharma Announces Free Helicopter Services For Tribal Patients And Attendants, Emphasises Skill Development

Andaman and Nicobar Lieutenant Governor Dr Dinesh Sharma announced free helicopter services for tribal patients…

2 hours ago

Amit Shah Accuses Rahul Gandhi Of Tarnishing India’s Image At International Summit

Union Home Minister Amit Shah criticised Rahul Gandhi over his remarks at the Bharat Summit…

2 hours ago

India U19 Captain Lakshya Raichandani Calls Asia Cup Triumph A ‘Very Good Experience’

India U19 captain Lakshya Raichandani described the team's Asia Cup victory over Pakistan as a…

4 hours ago

Delhi Metro To Begin Services At 4:30 AM On November 16 For Chhath Puja

Delhi Metro will start services at 4:30 AM on November 16 for Usha Arghya during…

5 hours ago